Down goes the house. It was originally built in the mid 1970's. We lived there for the last 18 years of it's life.
Our Demolition went smoothly - only a day to drop it, then the next to clear the site. (except keep our garden at the rear and the shed)
Friday 9th October 2009 - No Roof.
Monday 12th October 2009 - House going down. Site was cleared completely the next day.
Tuesday 20th October 2009 - Trenches dug. The plumbing pipes went in the next day.
Thursday 22nd October 2009 - Mesh and trenching covered.
Wednesday 28th October 2009 - Slab poured.
Friday 13th November 2009 - Frame started.
Monday 16th November 2009 - Roof frame completed.
Tuesday 17th November 2009 - Internal plumbing pipes put in. We now have a running water tap on the side of the house. (it is going to make watering the garden so much easier)
Wednesday 18th November 2009 - Windows and sliding doors are in.
Wow...no mucking around here. Something just about being done or delivered every day.